Reference Number |
7823159 |
Procuring Entity |
DEPARTMENT OF ENVIRONMENT AND NATURAL RES. - PENRO, ILOILO |
Title |
Construction of Small Water Impounding System of CENRO Guimbal located at Brgy. Lico, Alimodian, Iloilo, Brgy. Dagami, Maasin, Iloilo and Brgy. Trangka, Maasin, Iloilo |
Area of Delivery |
Iloilo |
Solicitation Number: |
2021-30 |
Trade Agreement: |
Implementing Rules and Regulations |
Procurement Mode: |
Negotiated Procurement - Two Failed Biddings (Sec. 53.1) |
Classification: |
Civil Works |
Category: |
Construction Management Services |
Approved Budget for the Contract: |
PHP 4,395,000.00
|
Delivery Period: |
150 Day/s |
Client Agency: |
|
|
Contact Person: |
EVELYN COLUMBRES MALIGAD BAC Secretariat Old Rotary Park, Fort San Pedro, Iloilo City Iloilo City Iloilo Philippines 5000 63-033-3351878 Ext.0 63-033-3369542 evelyn.maligad@yahoo.com |
|
Status |
Awarded |
Associated Components |
3 |
Bid Supplements |
0 |
Document Request List |
3 |
Date Published |
07/07/2021 |
Last Updated / Time |
31/12/2021 04:54 AM |
Closing Date / Time |
13/07/2021 13:00 PM |
Description |
|
Construction of Small Water Impounding System of CENRO Guimbal located at Brgy. Lico, Alimodian, Brgys. Dagami & Trangka, Maasin, Iloilo
BILL OF QUANTITIES DESCRIPTION QTY. UNIT MATERIAL COST UNIT PRICE COST I. Formworks/Project Billboard 1 Lump sum I. For Concrete Tank Construction Phase 1. Clearing and Grubbing 40 sq.m. 2. Excavation 30 cu.m. 3. Volume of Concrete for the Tank cu.m. Volume = 10.98 cu.m. Portland Cement 100 bags Sahara Cement 100 packs Concrete Sealant 8 gals. 3/4" Gravel 10.98 cu.m. Sand 5.49 cu.m. RSB 16 mm dia. Deformed Grade 60 1543.6 kgs. G.I. Wire # 16 23.15 kgs. 4. Roughing and Finishing Area = 47.72 sq. m. Portland Cement 16 bags Sand 1.29 cu.m. 5. Footing Volume = 0.80 cu. m. Portland Cement 8 bags Sand 0.40 cu.m. 3/4" Gravel 0.80 cu.m. RSB 16 mm dia. Deformed Grade 60 79.53 kgs. G.I. Wire # 16 1.19 kgs. 6. Columns Volume = 0.47 cu. m. Portland Cement 5 bags Sand 0.24 cu.m. 3/4" Gravel 0.47 cu.m. RSB 10mm dia. Deformed Grade 40 38.50 kgs. RSB 16 mm dia. Deformed Grade 60 32.82 kgs. G.I. Wire # 16 1.07 kgs. 7. Tie Beams Volume = 0.62 cu. m. Portland Cement 6 bags Sand 0.31 cu.m. 3/4" Gravel 0.62 cu.m. RSB 10mm dia. Deformed Grade 40 69.10 kgs. RSB 16 mm dia. Deformed Grade 60 104.15 kgs. G.I. Wire # 16 2.60 kgs. 8. Valve Box Volume = 0.05 cu. m. Portland Cement 1 bags 3/4" Gravel 0.5 cu.m. Sand 0.03 cu.m. RSB 16 mm dia. Deformed Grade 60 65.96 kgs. G.I. Wire # 16 0.99 kgs. 9. Ladder Rung Weight = 12.62 kgs RSB 16 mm dia. Deformed Grade 60 12.62 kgs II. Spring Box 1. Clearing and Grubbing 14 sq.m. 2. Excavation 3 cu.m. 3. Concrete Works Portland Cement 10 bags Sahara Cement 10 packs Super Thoroseal 5 gals. Crushed Sand 1 cu.m. 3/4" Gravel 2 cu.m. RSB 16 mm dia. X 6m 12 pcs. G.I. Wire # 16 10 kgs 5. Roughing and Finishing Portland Cement 10 bags Crush Sand 2 cu.m. 6. Footings Portland Cement 36 bags Crushed Sand 2.5 cu.m. 3/4" Gravel 5 cu.m. RSB 16 mm dia. X 6m 6 pcs. G.I. Wire # 16 3 kgs 7. Grouted Riprap Portland Cement 20 pcs. Boulders 2 cu.m. Crashed Sand 4 cu.m. 8. Ladder Rung RSB 16 mm dia. X 6m 2 pcs. III. Pipes and Fittings 2" Diameter Gate Valve 8 pcs. 2" Diameter G.I. Elbow 20 pcs. 2" Diameter G.I. Coupling 120 pcs. 2" Diameter G.I. Tee 10 pcs. 2" Diameter G.I. Pipe 100 pcs. Teflon Tape 200 rolls Reducer (2" dia. To 1" dia.) 10 pcs. Tee w/ Reducer (2" dia. To 1" dia.) 10 pcs. 1" Diameter G.I. Pipe 100 pcs. 1" Diameter Coupling 150 pcs. 1" Diameter G.I. Tee 60 pcs. 1" Diameter G.I. Elbow 50 pcs. 1" Diameter Gate Valve 8 pcs. IV. PAINTING WORKS Concrete Neutralizer 5 gals Flat Latex Primer 4 gals Color Latex (Semi-Gloss) 4 gals Masonry Putty 8 gals Assorted Sand Paper 32 pcs Paint Brush 2" 10 pcs Roller Brush 9" 10 pcs V. Distribution Line 3/4" Diameter Black Hose 200 mts. 3/4" Dia. Black Hose Coupling 20 pcs 3/4" Diameter Black Hose Tee 60 pcs 3/4" Dia. Black Hose Adaptor 60 pcs 1/2" Diameter Black Hose 300 mts. 1/2" Dia. Black Hose Coupling 10 pcs 1/2" Diameter Black Hose Tee 100 pcs 1/2" Dia. Black Hose Adaptor 60 pcs Plastic Faucet 60 pcs TOTAL MATERIAL COST TOTAL MATERIAL COST ESTIMATED LABOR COST (40%) CONSTRUCTION COST 20% CONTINGENCIES 10 % PROFIT 12 % VAT TOTAL CONSTRUCTION COST
Note: Computation of Bill of Quantities is good for one structure only @ 20 cu.m. at P73,250.00/cu.m. = P1,465,000.00
Brgy. Lico, Alimodian, Iloilo - 20 cu.m. @73,250.00 = P1,465.000.00 Brgy. Dagami, Maasin, Iloilo - 20 cu.m. @ 73,250.00 = 1,465,000.00 Brgy. Trangka, Maasin, Iloilo - 20 cu.m. @ 73,250.00 = 1,465,000.00 TOTAL P4,395,000.00 |
|
Line Items |
1 | Construction of Small Water Impounding System | CENRO Guimbal, Brgy. Lico, Alimodian, Brgy, Trangka & Dagami, Maasin, Iloilo | 1 | Lot | 4,395,000.00 |
|
|
|
|
Created by |
EVELYN COLUMBRES MALIGAD |
Date Created |
06/07/2021 |
|
|
|
|
|