Reference Number |
7391776 |
Procuring Entity |
DEPARTMENT OF ENVIRONMENT AND NATURAL RES. - PENRO, ILOILO |
Title |
Early Procurement Activity of CY 2021 for the Construction of Barasalon to Canauillian Pathway of PENRO, Iloilo |
Area of Delivery |
Iloilo |
Solicitation Number: |
2020-57 |
Trade Agreement: |
Implementing Rules and Regulations |
Procurement Mode: |
National Competitive Bidding |
Classification: |
Civil Works |
Category: |
Construction Management Services |
Approved Budget for the Contract: |
PHP 20,822,717.54
|
Delivery Period: |
300 Day/s |
Client Agency: |
|
|
Contact Person: |
EVELYN COLUMBRES MALIGAD BAC Secretariat Old Rotary Park, Fort San Pedro, Iloilo City Iloilo City Iloilo Philippines 5000 63-033-3351878 Ext.0 63-033-3369542 evelyn.maligad@yahoo.com |
|
Status |
Closed |
Associated Components |
5 |
Bid Supplements |
1 |
Document Request List |
11 |
Date Published |
30/12/2020 |
Last Updated / Time |
06/01/2021 15:27 PM |
Closing Date / Time |
19/01/2021 13:30 PM |
Description |
|
Republic of the Philippines Department of Environment and Natural Resources FORESTLAND MANAGEMENT PROJECT Province of Iloilo, Region VI BILL OF QUANTITIES Subproject Title/Name Construction of Barasalon - Canaullian Pathway Category Sub-Project Number Physical Test 2.463km Brgy./Mun./Province Suage Subwatershed, Municipality of Januiay, Iloilo, Region 6 Total Estimated Subproject Cost (PHP) 20,822,717.54 Project Description: Implementation Mode by contract "Construction of Barasalon - Canaullian Pathway with a total length of 2,463m. The maximum grade of the Pathway ranges from 22% to 27% higher than the grade criteria. The carriageway of all section is paved with 1.5 meter wide of Portland Cement Concrete Pavement (PCCP) whose thickness is 0.15 meter and 0.1 meter thick of subbase course, In critical curve, the PCCP pavement it widened to 2.0 to serve as a Parkway. Side drainage and cross structures were also provided. The subproject is located in the Suage Subwatershed, Municipality of Januiay, Iloilo. " Project Duration 300 Calendar Days (w/ 30 unworkable days) Equipment Needed Backhoe, 275 hp Cutting Outfit Wheel Tractor Walk Behind Roller, Vibratory Welding Machine Cargo Truck, 6 tons, 195 hp Plate Compactor, Vibratory, 5 hp Water Truck/Pump, 16000 lit Concrete Vibrator, 50mm dia., Gas Driven Dump Truck 4 to 6 cu. Yard w/ winch Concrete Screeder Portable Asphalt kettle One Bagger Mixer Bar Cutter, 20mm dia. Concrete Saw, 12", 5 lpm, Gas ITEM NO. DESCRIPTION WT. % QUANTITY UNIT UNIT COST TOTAL COST PART B OTHER GENERAL REQUIREMENTS B.4 (8) Permanent Monuments and Markers 1 ea. B.5 Project Billboard / Signboard 2 ea. B.7 Ocupational Safety and Health Program 1 L.S. B.9 Mobilization / Demobilization 1 L.S. TOTAL OF PART B PART C EARTHWORK 100 (1) Clearing and Grubbing w/ Stripping 1.22 ha. 102 (2)a Roadway Excavation (Surplus Common), including Disposal 6,356 cu.m. 102 (3)a Roadway Excavation (Surplus Soft Rock) 500 cu.m. 103 (1) Structure Excavation (Manual) 903 cu.m. 104 (1)b Embankment from Roadway Excavation 2,101 cu.m. 105 (2) Subgrade Preparation (Existing Pavement) 3,428 sq.m. TOTAL OF PART C PART D SUBBASE AND BASE COURSE 200 Aggregate Subbase Course, 0.10 m. thk. 344 cu.m. TOTAL OF PART D PART E SURFACE COURSES 311 (1)a.1.1 PCC Pavement, 0.15m. thk.,3000 psi, 28 days 3,439 sq.m. TOTAL OF PART E Part F DRAINAGE AND SLOPE PROTECTION 404 Reinforcing Steel, Grade 40 14,826 kg. 405 (1) Structural Concrete, 3000 psi, inc Formworks for Box Culvert 109 cu.m. 405 (2) Structural Concrete, 3000 psi, 28 days, for lined Canal 123 cu.m. 407 Lean Concrete 2 cu.m 503 Metal frams and Grating 6 lines 507 (1) Rubble Masonry 409 cu.m. 510 (1) Bed Course Granular Material (Gravel Bedding) 8 cu.m. 515 (3) Structural Backfill (Common Soil) 80 cu.m. TOTAL OF PART F Part G MISCELLANEOUS STRUCTURES 613(1)a Preformed Construction Expansion For Expansion Joint 5 sq.m 613(1)b Concrete Joint Sealant (Hot Poured Elastic) for Control Joints 310 kg. TOTAL OF PART G TOTAL ESTIMATED SUBPROJECT COST Pre-Bid Conference- January 7, 2021 at 1:30PM Submission & Opening of Bids - January 19, 2021 Cost of Bid docs- P21,000.00 |
|
Pre-bid Conference |
07/01/2021 |
1:30:00 PM |
DENR, PENRO, Iloilo Old Rotary Park, Brgy. Concepcion, Iloilo City |
|
|
Other Information |
Funding source is Fund 102 For Year 1 CY 2021 amounting to P11,452,494.65 For Year 2 Cy 2022 amounting to P 9,370,222.89 TOTAL AMOUNT of ABC amounting to 20,822,717.54 |
|
|
Created by |
EVELYN COLUMBRES MALIGAD |
Date Created |
29/12/2020 |
|
|
|
|
|